UCCS University Hall Renovation

Fuse Project Awards – Floorz

Award Category: Most Aggressive Timeline / Schedule

The UCCS University Hall Renovation required an accelerated delivery schedule to ensure the building was fully ready for occupancy prior to the start of the 2025 academic year. From initial pricing through final installation, the project demanded rapid mobilization, efficient submittal processing, and precise field execution.

Project Scope

  • 3,500 square yards of carpet tile
  • 12,000 square feet of LVT
  • 250 square yards of sheet vinyl
  • 10,000 linear feet of rubber base
  • Over 100 bags of skim coat preparation

Project Timeline

  • Bid Due: April 22
  • Contract / LOI Received: May 2
  • Installation Start: May 26
  • Installation Complete: First week of August

Within a four-month window, the team priced the project, executed the contract, completed all required submittals, and installed the full flooring scope across multiple material types. Careful coordination and accelerated sequencing allowed the work to be completed on schedule, ensuring the facility was ready for student occupancy when the academic year began.

The successful completion of this project under a compressed timeline highlights the team’s ability to mobilize quickly, manage parallel workflows, and deliver critical scope without compromising quality or schedule commitments.